BETWEEN 8:00AM AND 8:59AM AND THEN BETWEEN 10:01PM AND 11:00PM – THE WHOLE OF CIRCUITS BINONDO 19N; AND NORTH PORT 12H
Portion of Dagupan St. from F. Yuseco St. (Tayabas) to Claro M. Ave. including PNR Compound in Tondo.
Portion of Claro M. Recto Ave. from Jose Abad Santos Ave. (Manuguit) to and including Tahimik, San Antonio, Angalo, Asuncion, Sto. Cristo, C. Planas, Juan Luna and Antonio Rivera Sts.; Metrobank in Binondo, San Nicolas and Tondo.
Portion of Juan Luna St. from Claro M. Recto Ave. to and including PNB in Binondo.
Portion of Jose Abad Santos Ave. (Manuguit) and Reina Regente St. from P. Algue St. to near Veronica St. including Alvarado St. in Binondo and Tondo.
REASON: Maintenance work inside Meralco – Binondo substation.