June 5, 2019 - Quezon City (Doña Imelda, Santol and Tatalon)
BETWEEN 8:00AM AND 8:30AM AND THEN BETWEEN 2:30PM AND 3:00PM – PORTION OF CIRCUIT STA. MESA 55F
Portion of Casiana, Silencio and Bayani Sts. from Meralco - Sta. Mesa substation along Santol St. to G. Araneta Ave. including T. Arguelles St. in Bgys. Santol and Doña Imelda.
Portion of G. Araneta Ave. from Bayani St. to Victory Ave. including Villa España Subd.; and Sto. Niño St. in Bgys. Doña Imelda and Tatalon.
BETWEEN 8:00AM AND 3:00PM – PORTION OF CIRCUIT STA. MESA 55F
Portion of G. Araneta Ave. from near Victory Ave. to and including 7-Eleven Store in Bgy. Tatalon.
Portion of Kaliraya St. from Kaliraya Bridge to and including Tuayan, Lapu-Lapu, Lumot, Cabalata, Mazaraga, Manunggal and San Isidro Sts.; Villa España II Subd. and ROTC Hunters Subd. in Bgy. Tatalon.
Portion of Victory Ave. from Diosdado P. Macapagal Elementary School to near Kaliraya St. in Bgy. Tatalon.
REASON: Relocation of facilities affected by ongoing construction of DPWH Skyway Project along G. Araneta Ave. in Bgy. Tatalon, Quezon City.