DISCONTINUATION OF BIDDING
CONTRACT CAPACITY OF 1,200 MW (NET), COD 2024
To all interested bidders:
In relation to the Second Invitation to Bid published last 23 and 30 December 2019 for the above-captioned contract capacity, we would like to give notice that Meralco has updated its Power Supply Procurement Plan ("PSPP") and Distribution Development Plan (“DDP”), taking into account actual demand for 2019 and acquisition of demand-side and supply-side resources to costeffectively meet needs of customers, for submission this coming March 2020;
thus, it was determined by MERALCO that the Bidding for the greenfield baseload capacity of 1,200 (net), COD 2024 shall be discontinued. Upon approval by DOE, Meralco in due time will invite bidders to participate in the bidding for greenfield baseload capacity of 1,800 MW (net), COD 2024-2025. For your guidance and information.
Issued on 6 March 2020.
Third Party Bids and Awards Committee (“TPBAC”)
Manila Electric Company
Atty. Ferdinand A. Domingo
Chairman